The Indonesian power sector has to date been the most successful of the infrastructure sectors in attracting private sector investment, and debt financing from both international and domestic lenders. The state-owned power utility company, PT PLN (Persero), has since the very early private sector power generation projects of the 1990s developed a robust and bankable Power Purchase Agreement (PPA) model for large-scale power projects. Whilst there have been the inevitable "tweaks" to the PPA model over the past 20 years (coming from both the PLN side of the negotiation table as well as the developer/lender side), the model for large-scale power projects remains today a solid one, and one that is able to mobilise private sector equity and debt funding. Recent flagship projects that demonstrate the success of the current PPA model include the Central Java 2 x 1000MW project, the Sarulla Geothermal Project and many others.
However, the Ministry of Energy and Mineral Resources on 19th January 2017 issued Regulation No. 10/2017 on Principles of Power Purchase Agreements ("MEMR Reg. 10"), which, for the first time in any material way, seeks to impose certain requirements as to what provisions must be built into PPAs in the power sector. Other power sector regulations have, from time to time, touched lightly on certain aspects of the PPAs (e.g., the mini-hydro regulations provide that if the developer fails to complete construction of the project within the required timeframe, the tariff under the PPA should be subjected to a discount as a form of penalty), but the key bankability and risk allocation points have been left to negotiation between PLN and the developers (and lenders). However, with the passing of MEMR Reg. 10, PLN's freedom to negotiate terms has been curtailed.
The regulation applies to all power projects, including geothermal, biomass and hydropower plants.
However, the regulation does not apply to intermittent power projects (i.e., wind and solar, regardless of size), mini-hydro power plants (below 10MW), biogas power plants and waste-to-energy power plants. These categories of power plants will be subject to their own specific regulations.
Additionally, the transitional provisions of the regulation provide that these new PPA requirements will not apply to PLN procurement processes where bid closing has already occurred, where PLN has signed letters of intent with developers or where the PPA has already been signed or where there is any amendment to an existing PPA.
For geothermal projects where the auction process to award the geothermal concession has already been completed, or projects where the winner has been declared, or where the PPA has been signed, they too will not be subject to the regulation.
For all relevant projects where the procurement processes are ongoing and bid closing has not occurred, the new requirements must be complied with. Accordingly, we suspect that PLN will soon be issuing extension notices for ongoing bid processes to give PLN enough time to adapt the model PPAs contained within those bid packages to the requirements of MEMR Reg. 10.
MEMR Reg. 10 introduces a number of new mandatory concepts which are certainly likely to give rise to concerns with developers and their lenders:
However, Article 8 of MEMR Reg. 10 now provides that both PLN and the developers will take responsibility for Government force majeure events. Government force majeure is defined in the regulation as "changes in policies or regulations" (and therefore appears to capture changes in law) although somewhat confusingly, the same term is used elsewhere in the regulation to mean only "changes in government policy" (and not changes in law). Aside from change in laws and policies, the other form of "government force majeure" typically captured by the PPAs is the unjustified action or inaction of Government (e.g., delays in issuing permits and approvals and revocation of licences without cause). Accordingly, following the strict reading of MEMR Reg. 10, it is still permissible for PLN (as it traditionally has done) to take responsibility for these unjustified actions or inactions of Government; however, in the case of changes in laws and policies, the regulation appears to require both PLN and the developer to bear that risk, with the PPA to further detail how that risk is allocated. It may be then that PLN seeks to build some form of grace period, or cost buffer, into the effects of changes in laws and regulations. For example:
However, Article 28 of MEMR Reg. 10 also deals with allocation of risk for changes in laws and changes in government policy. It provides that:
The treatment of change in law reflects the risk allocation treatment under the current generation of PPAs. However, the treatment of change in policies would appear to conflict with Article 8 – which appears to allow for a sharing of the risk of changes in government policy (as opposed to simply releasing PLN from its obligations).
One reading of Article 28 which would result in it being consistent with Article 8 is that Article 8 applies to temporary shutdowns due to changes in government policy (e.g., if the plant is shut down for one month, then PLN does not need to pay deemed dispatch payments for the first 14 days, but thereafter has to start making deemed dispatch payments) whereas Article 28 applies to prolonged government events (e.g., if a government change in policy results in the plant being shut down for longer than 180 days, then the PPA can be terminated). The intent of Article 28 does at least appear to make clear that where the PPA is terminated due to a government change in policy then PLN has no obligation to buy out the project.
So whilst the regulation appears to continue to give PLN freedom to (i) cover the cost increase and plant downtime consequences of unjustified Government actions or inactions, and (ii) cover the cost increase implications of changes in law, the position in relation to the loss of revenue caused by plant downtime due to changes in law and changes in government policy is somewhat unclear.
Statements made by the Government at the public launch of MEMR Reg. 10 held on 2nd February 2017 suggest that the Government's intention with respect to Article 28 was not to change the longstanding risk allocation that has existed under the current PPA model related to the compensation for changes in Government policy, but instead it was to confirm that a power generator had the comfort of knowing it would be relieved from any liability in the event of such changes in Government policy. However, the text of the regulation itself does appear to fundamentally change the risk allocation on this point – making it clear that PLN is similarly relieved from all obligations (which would include obligations to buy out the project) if such changes in Government policy occurred leading to a shutdown of the project.
New performance penalties for failing to meet ramp rates
The existing generation of PPAs typically only penalise developers for failing to meet the availability targets – i.e., if the availability target (e.g., 80%) is not met (e.g. actual performance was only 78%), then PLN will only pay the developer for the 78% of actual availability, and will penalise the developer a further 2% for the 2% shortfall between the guaranteed availability and the actual availability so the developer would receive net 76% for that month.
In the most recent base-load PPAs, PLN has sought to introduce penalties for failing to meet reactive power requirements as well as failing to comply with frequency requirements.
MEMR Reg. 10 also now requires the PPA to have a penalty regime for failing to meet ramp up and ramp down instructions from PLN dispatch centres.
MEMR Reg. 10 now embeds certain shareholding retention obligations – prohibiting the transfer of ownership in power generators prior to the plant achieving commercial operation. What is not entirely clear is whether a transfer of shares between the founding sponsors of the project is permitted (e.g., if Company A and Company B are the two founding 50%:50% sponsors of the project, but then Company B is unable to fund cost overruns etc. and Company A steps in to fund such that Company B is diluted to 40% and Company A increases to 60%). We believe that because the ownership of the power generator has not changed (i.e., it is still collectively owned by the founding sponsors), such flexibility should be permitted under the PPA without breaching the restriction.
After commercial operation, the transfer of shares in the power generator is only permitted with the approval of PLN (and must be reported to the Government). In the existing generation of PPAs, there is generally full freedom of the sponsors to sell their shares in the power generator after the fifth anniversary of commercial operation. We do believe that there is flexibility in the wording of the regulation to allow for a "pre-approval" mechanism to be built into the PPA to deal with these changes of shareholding – for example, if a sponsor wishes to sell, the sponsor should offer the shares to PLN, and if PLN chooses not to exercise its right to buy those shares, the sponsor is free to sell the shares to a third party (at a price not less than that offered to PLN) and PLN is deemed to have approved such sale.
A transfer from a sponsor to its (at least) 90%-owned affiliate entity is permitted (therefore giving sponsors the flexibility to structure their ownership of the power generator to meet their internal corporate and tax requirements).
Clearly, the broad principles set out in MEMR Reg. 10 will need to be translated by PLN and developers into detailed contractual provisions in the PPAs themselves. The Government has indicated in its public statements on the regulation that the main aim of the regulation was not to impose any changes to the existing PPA model used by PLN, with the exception of making a BOOT model compulsory for all the power projects falling within the scope of the regulation. The wording of the regulation, however, appears to have much further reach.
Whilst some of these broad principles do ring alarm bells in terms of the future bankability of the Indonesian PPA model, it is hoped that the flexibility given by "the devil being in the details" can be used to ensure that this new generation of PPA is still a model on which, like the PPA generations that preceded it, private sector investors and developers are willing to invest the billions of US dollars needed to achieve Indonesia's electrification goals.
Hadiputranto, Hadinoto & Partners, Member of Baker & McKenzie International - 3rd february 2017
Capital: Jakarta
Population: 259 million (2016)
Currency: Indonesian Rupiah
Nominal GDP: $936 billion USD (IMF, 2016)
GDP Per Capita: $3,620 USD at Current Prices (IMF, 2016)
GDP Growth: 5.0% (2016)
External Debt: 36.80% of GDP (BI, Q2 2016)
Ease of Doing Business: 91/190 (WB, 2017)
Corruption Index: 90/176 (TI, 2016)
Investment in Indonesia’s Electricity Sector; Sparks of Life
Indonesia’s Geothermal Energy Sector; Latest Advancements
Indonesia’s Subsidies on Electricity Powered Down
PLN Issues 10-Year Electricity Supply Business Plan (RUPTL) for 2016-2025
New Presidential Regulation to Accelerate 35GW Power Generation Programme